JONESBORO, AR – (Newsfile Corp. – July 19, 2022) – Camfil APC is pleased to announce a series of activities leading up to the opening of its new facility on Nestle Road in Jonesboro, Arkansas. Camfil APC air pollution experts have gathered hours of video footage, including drone overflights and time-lapse videos, of the dismantling and construction of Camfil APC facilities since the tornado that struck in Spring 2020. By documenting the progress of the journey, Camfil will be able to share the excitement of the transition into the state-of-the-art building with customers and stakeholders over the coming months.​

Can't see this picture?  Visit: https://images.newsfilecorp.com/files/8568/131341_8fa803d58426ebdc_001.jpg

CAMFIL AIR POLLUTION CONTROL (APC) NEW MANUFACTURING PLANT

To view an expanded version of this graphic, please visit:
https://images.newsfilecorp.com/files/8568/131341_8fa803d58426ebdc_001full.jpg

John Williams, Senior Project Manager, gave an insight into the next and final steps of building construction. “Construction continues both inside and outside of our new factory. Additionally, we are awaiting key electrical components for factory and office infrastructure that have been delayed,” Williams said. “With any luck, we should see these items in early July.”

Roof installation continues as Camfil awaits delivery of roof clips damaged by high winds earlier this spring. Williams said that over the next few weeks the factory will be fully enclosed and take shape and begin to “look more like a Camfil factory.”

“Our building infrastructure and equipment continues in July with equipment shipments including air compressors, compressed air dryers, nitrogen generation systems, compressed air circuitry, weld gas linings and nitrogen lines on-going,” Williams said. “Our community groups are working to complete the extension of the underground utilities on the site, which is due to be completed in July with the final connections to Camfil’s new factory.”

Final…